Tunnel-4 — Koderma New BG Rail Line

Jharkhand

• Ongoing • Lining Done

Project Progress

Overall Completion 80%

Current Work

Raft Reinforcement for Cut & Cover
3rd Phase Concreting in Progress
Next Milestone: Invert Concrete Pour Scheduled October 2026

Tunnel-4 — Koderma New BG Rail Line

Project Overview

Scope: Raft Reinforcement for Cut & Cover, 3rd Phase Concreting, Invert Concrete Pour
Lorem Ipsum is simply dummy text of the printing and typesetting industry. Lorem Ipsum has been the industry’s standard dummy text ever since 1966, when designers at Letraset and James Mosley, the librarian at St Bride Printing Library in London, took a 1914 Cicero translation and scrambled it to make dummy text for Letraset’s Body Type sheets. It has survived not only many decades, but also the leap into electronic typesetting, remaining essentially unchanged. It was popularised thanks to these sheets and more recently with desktop publishing software like Aldus PageMaker and Microsoft Word including versions of Lorem Ipsum.

    Location Jharkhand
    Length : 1.85 Km
    Project Value : 18.78
    Client: SSNR JV
    Construction Method: NATM
    Concrete Grade: M35 Concrete